TestRail milestone questions


#1
  1. How do I close an old milestone that is completed

  2. Is there a way to copy an old milestone and prepare it for the next sprint without the tasks showing up for people in their ‘to do’ until it is ready?

Thanks


#2

Hello Cathie,

Thanks for your posting. You can mark a milestone as completed by editing it and checking the “This milestone is completed” checkbox.

While you cannot copy entire milestones (and its test runs/plans), you can simply add the new milestone and then rerun the test runs/plans of the previous milestone (via the Rerun button when viewing a test run/plan). The test runs/plans will only appear on the todo/task list once you’ve assigned the test runs/plans (tests) to users.

I hope this helps!

Regards,
Tobias