Milestone Start/End Dates get over written/dropped by started_on and completed_on

The start_on, due_on dates for milestones seem to get blanked out or overwritten/ridden by the started_on and completed_on when those dates are captured.

I need both dates to stay… the start_on/due_on equates to planned… the started_on and completed_on represent the actual.

Is there a reason these dates are getting blanked out?

Hi Ken,

Sorry for the late reply, this certainly not ideal behavior. Beyond making sure you save the milestone edit page there’s nothing else that needs to be done. If you believe this is a bug, feel free to send in any relevant information (screenshot, error messages, video) you have to contact@gurock.com for further investigation.