Hello,

we are using TestRail as a repository for our tests, part of which are executed automatically.
For the manual ones, it’s easy to set up the elapsed time, thank to the Play button.

For the automatic ones, after we finish our automatic tests, we have to mark them as “Passed” and specify an elapsed time.
We know the amount of time necessary for the entire section, not for the single test cases.
So, let’s say that we ran automatically 10 of those test cases and they took 25 minutes. Is there a way to select those test cases and set 25 minutes as the total elapsed time and then it’s TestRail setting every test elapsed time to 25min/10?

Thanks in advance